GIR Construction Update: Spring 2022

I-95 MEDIAN, UNDERSIDE WORK CONTINUES AT GIRARD INTERCHANGE

March 29, 2022 – Median construction continues this spring (see photo below) at the northern end of the Interstate 95/Girard Avenue Interchange along with continuing installation of ground-level improvements at the interchange under I-95.

Temporary construction barriers remain in place and occasional daytime and off-peak travel restrictions may be in place on both northbound and southbound I-95 through mid-2022 as work is completed in the center of the interstate. Later this spring, all barriers should be removed until the next phase of the overall Girard Avenue Interchange project begins in 2023 south of the on-off ramps.

(Under the Section GR5 and GR6 contracts, several I-95 viaducts and other structures beginning at Frankford Avenue and progressing south to near Race Street will be replaced. Northbound reconstruction, Section GR6, is scheduled to begin in 2023. Section GR5 will reconstruct the southbound side beginning in 2026.) 

Ongoing work beneath the new, mile-long I-95 viaducts between Palmer and Ann streets (see photos below) includes creation of a variety of public spaces, including construction of a multi-use trail that will be incorporated into the Delaware River Greenway that stretches along the waterfront. PennDOT is also installing cobblestone pathways, dyed concrete pavement, rain gardens, rock-lined drainage basins, strips of planted grass areas, benches, trees, and small public parking areas.

Pedestrian-friendly LED street and overhead lighting will illuminate the underside area when construction of these sustainable, ground-level improvements that are designed to benefit residents living in neighborhoods along the interstate finishes in summer 2022.

During the past three years of construction on the $315 million Section GR4 contract, PennDOT has rebuilt and widened southbound I-95, including replacement of the mile-long southbound viaduct between Ann and Palmer streets, rebuilt the southbound off- and on-ramps, and installed noise barrier walls along southbound I-95. (The northbound viaduct was replaced under Section GR3 construction that ended in 2018.)

The GR4 contract also includes installation of Intelligent Transportation Systems (ITS) components that are currently under construction at various locations across the region (on I-95, U.S. 1 and PA 332). Those components will assist PennDOT and the City of Philadelphia with traffic and incident management on the region’s highways.

The GR4 improvements in place between Allegheny Avenue and Palmer Street connect to a 1,200 foot-segment of I-95 south of the interchange that was reconstructed in 2013-2015 under the GR2 contract.   

PennDOT has invested more than $660 million since 2009 rebuilding this section of I-95 in Philadelphia. Two additional project sections, GR5 and GR6, will complete the reconstruction of I-95 from Allegheny Avenue to the Interstate 676 Interchange between 2023 and 2029.