BSR Construction Update: Fall 2026

Northbound I-95 Reconstruction, Improved Interchange Construction at Bridge Street

October 8, 2026 – Reconstruction and widening of the northbound side of Interstate 95 at the Bridge Street Interchange (Section BS2) began in late summer following a traffic shift that moved northbound vehicles to the center area of the work zone between Margaret Street and Carver Street in Northeast Philadelphia.

PennDOT’s contractor shifted southbound traffic onto the new pavement in late May, and over the summer, prepared the middle of the interstate for the current traffic pattern.

Removal of the existing northbound pavement, construction of several retaining walls along Tacony Street to support northbound widening (see right), and demolition of the northbound viaduct over Tacony and Bridge streets (see above) will be the major focus of work for the remainder of the year, along with the demolition and construction of the northbound side of a new bridge over Fraley Street (see below).

Construction of a new Bridge Street Interchange this fall finds crews building the northbound half of the new underpass that will loop the new southbound off-ramp under I-95 and connect with a new signalized intersection on Tacony Street. In addition, a new ramp structure that will be constructed over Tacony Street from an abutment in place on the east side of the roadway and connect with I-95 North from the Delaware Avenue Extension will continue to be built.

The Extension will eventually connect with Delaware Avenue from its current terminus along the river near Buckius Street. The bulk of the extension will be built under Section BS5, which is tentatively scheduled for construction beginning in 2027.

Northbound reconstruction has reduced southbound Tacony Street to a single lane for much of the distance between Van Kirk and Bridge streets. An extensive pedestrian detour will remain in place in this area through 2027. The construction team will continuously monitor conditions on Tacony Street and make any changes to the traffic pattern and its traffic signals that are feasible in an effort to reduce delays through the project area. Motorists are advised to explore alternate routes through the construction if possible.

The southbound exit at Bridge Street remains closed and detoured to the Aramingo Avenue exit at the Betsy Ross Bridge Interchange. Northbound I-95 motorists heading to Bridge Street will permanently use the exit at the Betsy Ross Bridge and take Aramingo Avenue north to Bridge Street.

The original northbound on-ramp from Bridge Street was closed in August for the start of northbound reconstruction. The new on-ramp at Tacony Street is expected to be completed in late 2027. During construction, local traffic heading to northbound I-95 is being diverted to the northbound on-ramp from Milnor Street at the Cottman Avenue Interchange.

Work to rebuild and widen the southbound side of I-95, including a new southbound viaduct over Bridge and Tacony streets (see above), finished last spring, marking completion of the first major stage of PennDOT’s $268 million I-95/BS2 project to reconstruct and widen I-95 in both directions between Margaret Street and Carver Street in Northeast Philadelphia.

Work on BS2 is being coordinated with northbound reconstruction currently underway at the Betsy Ross Bridge Interchange immediately to the south.

Section BS2, the second of five contracts to reconstruct Interstate 95 and improve the Bridge Street Interchange, is expected to be completed in 2028. PennDOT completed Section BS1 reconstruction to rebuild and widen I-95 between Levick and Carver streets in early 2023.

During all upcoming Section BS2 work, three travel lanes in each direction will remain open during peak travel times, though periodic off-peak lane closures may be in place on I-95 during certain stages of construction.

James J. Anderson Construction, of Philadelphia, is the general contractor on Section BS2.

​