October 8, 2026 – Northbound construction at the Interstate 95 Betsy Ross Bridge Interchange (Section BR3) this fall finds crews across the expansive work zone excavating the base for four new travel lanes, rebuilding bridges, installing and moving utilities, and building retaining walls to support the addition of a fourth lane.
Excavators have removed the old northbound pavement from three through lanes and two auxiliary lanes that collected traffic exiting and entering I-95 from the interchange on Aramingo Avenue and the Betsy Ross Bridge. The excavated roadway material is being stored on site for use in future stages of the project.
Northbound bridges over the Frankford Creek and Orthodox/Pearce Streets have been demolished, and the Lefevre Street overpass will be taken down this fall. Pearce Street will be realigned to connect to Orthodox Street on the east side of I-95. Foundation and abutment construction (see above) for these three structures will continue throughout the remainder of the year.
Water, sewer, electric, gas (see below), and fiber optic utilities are being installed or relocated across the project area.
The work is being done under PennDOT’s $355.3 million Section BR3 project to reconstruct, widen, and improve northbound I-95 between Wheatsheaf Lane and Margaret Street in Northeast Philadelphia.
Section BR3 work is being coordinated with Section BS2 reconstruction immediately north and Section AF3 reconstruction immediately south.
Section BR3, the third of five contract sections to reconstruct and improve I-95 at the Betsy Ross Bridge Interchange, continues PennDOT’s long-term commitment to rebuilding and improving the aging I-95 infrastructure in Pennsylvania.
In addition, two ramps are being rehabilitated, two ramps are being replaced with at-grade fill, and new northbound sound barrier walls will also be erected during later stages of construction.
The southbound side of I-95 at the Interchange will be completed under the BR4 contract that is tentatively scheduled to go to construction in 2029 or 2030.
PennDOT completed Sections BR0 (2017) and BR2 (2023) that reconstructed numerous ramps and bridges at the interchange. Ground-level and utility work was also completed under these projects. Go here for more details.
Haines & Kibblehouse Construction of Skippack, PA, is the BR3 general contractor.