AFC Construction Update: Fall 2026

Northbound I-95 Construction Ramping Up This Fall at the Allegheny/Castor Interchange in Northeast Philadelphia

November 2, 2026 – Following implementation of a new work zone traffic pattern in early October that moved northbound traffic to the center of the interstate, construction activities began full-scale on northbound Interstate 95 at the northern end of the Allegheny/Castor Avenue Interchange in Northeast Philadelphia.

Construction activities this fall will focus on removal of 1.3 miles of the existing three lanes of northbound concrete pavement between Tioga Street and Wheatsheaf Lane and demolition and subsequent construction of the northbound side of bridges over Venango Street, Castor Avenue and Wheatsheaf Lane.

Construction of new abutments/wingwalls at the bridges will include pile driving during the day. Drilled micropiles will be used in the areas closest to residents to cut down on noise and vibration. Periodic surface street closures and lane shifts may be in place during demolition activities.

The northbound ramp from I-95 North that vaulted over Castor Avenue to the Betsy Ross Bridge is also being removed under the $311 million Section AF3 contract. The ramp was relocated to access the Castor Avenue on-ramp, giving northbound I-95 drivers access to the Bridge.

The existing on-ramp at Castor Avenue will remain open except for two or three weekends when it will be closed and detoured during a later stage of construction. Also during a later stage of the Section AF3 project, new northbound on and off-ramps will be built at Castor Avenue. The new on-ramp will include a ramp to the Bridge.

Construction crews will also begin installation of the project’s stormwater drainage system.

Numerous utilities will be installed or relocated along the northbound side of I-95 and nearby surface streets during northbound reconstruction. 

Noise walls will also be constructed along both sides of I-95 in the AF3 project area during later stages of construction.

The AF3 work zone traffic pattern will provide three through lanes for northbound vehicles during peak travel times. The southbound side of the work zone remains open to four lanes for peak hour traffic.

Section AF3 construction is being coordinated with northbound reconstruction and widening currently underway on Sections BR2 and BS2 at the adjacent Betsy Ross Bridge and Bridge Street interchanges.

Section AF3 will widen I-95 to four lanes. The southbound side of I-95 between Wheatsheaf Lane and Tioga Street under the AF3 project will be reconstructed and widened following completion of work on the northbound side in 2028.

The entire Section AF3 contract is scheduled to be completed in late 2031. It is the third of four contracts to reconstruct and improve I-95 at the Allegheny/Castor Interchange as part of Section AFC.

Sections AF1, completed in 2020, and AF2, completed in 2023, improved surface streets in the vicinity of the interchange. Section AF4 is expected to begin at the completion of AF3. That contract will complete reconstruction at the interchange by rebuilding the I-95 between Tioga and Ann Street and improving access to and from I-95 at Allegheny Avenue.

South State Inc., of Bridgeton, NJ, is the general contractor on the 100 percent federally funded AF3 project.