AFC Construction Update: Summer 2020

July 27, 2020
Completion of paving between Westmoreland Street and Allegheny Avenue, traffic signal upgrades... will bring PennDOT's $32 million project to reconstruct and improve Richmond Street in the vicinity of the Interstate 95 Allegheny Avenue Interchange in Port Richmond to a close after more than two years of construction...
Read More

GIR Construction Update: Summer 2020

July 20, 2020
Construction resumed in late April following a six-week shutdown due to the COVID-19 virus on the replacement of the southbound Interstate 95 viaduct between Palmer Street in Fishtown and Ann Street in Port Richmond...
Read More

BS4/H04 Construction Update: Summer 2020

July 1, 2020
Construction continues on the northbound side of the new Aramingo Avenue bridge over Frankford Creek at the I-95/Betsy Ross Bridge Interchange where crews have set deck beams and begun construction of the bridge's two northbound travel lanes...
Read More

GIR Construction Update: Spring 2020

May 12, 2020
Demolition of the existing southbound viaduct has been completed (except for a small section that remains during construction of the new Aramingo Avenue bridge through the interchange) and segments of the new structure are at various levels of completion...
Read More

BS4/H04 Construction Update: Spring 2020

May 12, 2020
Construction on the surface streets at the Interstate 95/Betsy Ross Bridge Interchange has resumed following the COVID-19 shutdown in early spring...
Read More

AFC/Richmond Street Construction Update: Spring 2020

May 12, 2020
Roadway, sidewalk, and utility improvements to Richmond Street between Ann Street and Aramingo Avenue in Port Richmond have been substantially completed...
Read More