GIR Construction Update: Spring 2020

May 12, 2020
Demolition of the existing southbound viaduct has been completed (except for a small section that remains during construction of the new Aramingo Avenue bridge through the interchange) and segments of the new structure are at various levels of completion...
Read More

BS4/H04 Construction Update: Spring 2020

May 12, 2020
Construction on the surface streets at the Interstate 95/Betsy Ross Bridge Interchange has resumed following the COVID-19 shutdown in early spring...
Read More

AFC/Richmond Street Construction Update: Spring 2020

May 12, 2020
Roadway, sidewalk, and utility improvements to Richmond Street between Ann Street and Aramingo Avenue in Port Richmond have been substantially completed...
Read More

AFC/Richmond Street Construction Update: Winter 2019/2020

January 16, 2020
Roadway and sidewalk construction on Richmond Street has been completed between Ann and Westmoreland Streets in Port Richmond, and work on several additional improvements along the corridor will continue through early 2020.
Read More

Betsy Ross Bridge Interchange Construction Update: Winter 2019/2020

January 16, 2020
Construction at the Interstate 95/Betsy Ross Bridge Interchange continues this winter on improvements to surface streets that funnel traffic to and from the interchange.