BSR Progress Photos

Shown below are all the current photographs of the project, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

8.20.19_H04-2
August 26, 2019
A crew finishes installation of the new storm sewer on Torresdale Avenue near the new intersection with the Adams Avenue Connector.
7.24.19_BS4-2
August 08, 2019
The southbound side of the Aramingo Avenue bridge over the Frankford Creek is finished. Work has briefly shifted to the middle before they proceed to the northbound side.
6.11.19_BS4-2
June 14, 2019
Workers build the decorative parapets on the southbound side of the newly constructed Aramingo Avenue bridge over the Frankford Creek.
6.5.19_BS4
June 05, 2019
The new concrete deck is in place over the Aramingo Avenue bridge over the Frankford Creek.
5.21.19_BS4-2
June 05, 2019
A crew installs a sewer main on Aramingo Avenue.
4.25.19_BS4-1
May 01, 2019
Workers install rebars on the Aramingo Avenue bridge over the Frankford Creek.
4.25.19_BS4-3
May 01, 2019
Crews prepare to lay the deck for the new Aramingo bridge over the Frankford Creek.
4.25.19_BS4-2
May 01, 2019
The subbase is in place for the Adams Avenue Connector.
3.6.19_H04-2
March 06, 2019
Deck construction continues on the west side of the new Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
2.19_BS4-3
February 04, 2019
Workers weld sections of a new gas main being installed under Aramingo Avenue at the Betsy Ross Bridge Interchange.