• Follow Us on Twitter

BSR Progress Photos

Shown below are all the current photographs of the project, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

7.18.18_H04-1
July 20, 2018
An inspector looks on as rock is excavated for construction of the west side of the new Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Bridge Interchange.
5.9.18_BS4-4
May 10, 2018
Pile driving at the Aramingo Avenue bridge over Frankford Creek at the Betsy Ross Interchange
5.2.18_BS4
May 03, 2018
An operator completes demolition of the pier foundations of the old Aramingo Avenue bridge over Frankford Creek.
4.2.18_Richmond Street
April 04, 2018
Installation of new PGW gas mains continues along the northbound side of Richmond Street between Ann Street and Allegheny Avenue.
4.2.18_Adams Ave Connector
April 04, 2018
Workers cover a newly-placed section of the concrete base for a section of the Adams Avenue Connector.
Aramingo Bridge Demo 3.18
February 12, 2018
Crews have begun work to demolish the western half of the Aramingo Avenue bridge over Frankford Creek. The new bridge will be wider to accommodate improvements to the Betsy Ross Bridge/Aramingo Avenue Interchange.
Aramingo 3.18
February 12, 2018
Southbound Aramingo Avenue is widened to accommodate the new ramps at the Betsy Ross Bridge/Aramingo Avenue Interchange.
Adams Avenue Connector 1.18
January 26, 2018
A crew installs a drainage box for the Adams Avenue Connector.
Adams Avenue Connector
December 27, 2017
The Adams Avenue Connector between Torresdale and Aramingo avenues progresses toward Aramingo Avenue.
12.7.17 Adams Avenue Connector
December 08, 2017
With the Conrail bridge over Adams Avenue in the background, PennDOT is extending Adams Avenue from Torresdale Avenue to Aramingo Avenue as part of improvements to the I-95 Betsy Ross Bridge Interchange.