CPR Progress Photos

"What are they doing there?"

Below are photos showing construction progress or illustrating unique concepts, materials or approaches in use at Cottman Avenue. Images are in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails. If you'd like more information about what you are seeing, send us an email and we'll be glad to fill you in.

6.23.16_CPR-1
June 29, 2016
The asphalt base pavement between bridges along northbound I-95 at Cottman Avenue. The asphalt will be topped with 14" of concrete during paving operations this summer.
6.23.16_CPR-2
June 29, 2016
A new highway light is installed along the northbound lanes at the Cottman Avenue Interchange.
6.10.16_CPR-3
June 13, 2016
A section of northbound I-95 at the Cottman Avenue Interchange is prepared for paving.
6.10.16_CPR-1
June 13, 2016
Preparing to pave the northbound lanes at Cottman Avenue
6.10.16_CPR-2
June 13, 2016
Construction of parapets atop a retaining wall that supports widening of the northbound side of I-95 at the Cottman Avenue Interchange.
6.10.16_CPR-4
June 13, 2016
A new water main installation at the Cottman Avenue Interchange
6.1.16_CPR-3
May 31, 2016
Workers set a guide line for the finished paving grade of a section of I-95 north between the Cottman and Bleigh avenues.
6.1.16_CPR-1
May 31, 2016
A section of northbound I-95 at the Cottman Avenue Interchange is ready for paving.
5.12.16_CPR-3
May 13, 2016
Deck beams in place over the on-ramp to I-95 north from Princeton Avenue: The overpass will be paved once deck steel is in place.
5.5.16_CPR-1
May 06, 2016
Deck beams are in place for the I-95 north bridge over Princeton Avenue, which is being extended from Torresdale Avenue to Milnor Street. Note the ornamental finish on the abutment wall.