Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

1.10.17_BR0-8
January 10, 2017
Construction of piers for the center section of a new ramp from Aramingo Avenue to the Betsy Ross Bridge
1.10.17_CPR-7
January 10, 2017
The eastbound only extension of Princeton Avenue between Torresdale Avenue and Milnor Street will be finished and open later this year.
1.10.17_CPR-3
January 10, 2017
Two of three lanes on the SB off ramp to Bleigh Avenue are open. The third, left turn lane will be open at the completion of improvements to Bleigh Avenue later this year.
1.10.17_CPR-5
January 10, 2017
Four lanes in each direction are now open at the Cottman Avenue Interchange.
12.14.16_BR0-1
December 16, 2016
Workers assemble formwork for support columns for a new ramp from Aramingo Avenue to the Betsy Ross Bridge.
12.14.16_CPR-2
December 16, 2016
Barrels have replaced concrete barriers at the work zone between Cottman Avenue and Bridge Street. Four lanes in each direction are scheduled to be opened between the interchanges this week.
12.14.16_GIR-4
December 16, 2016
Workers install shoring to support the walls of the trench that was excavated for placement of a new sewer main down the middle of Delaware Avenue.
12.14.16_GIR-5
December 16, 2016
Sewer main construction down the middle of Delaware Avenue, one of the utility upgrades that are part of the project to rebuild I-95 at the Girard Avenue Interchange.
12.14.16_GIR-1
December 16, 2016
Continued beam setting for the new northbound viaduct at Girard Avenue
12.14.16_CPR-4
December 16, 2016
A crew finishes median barrier construction at the Cottman Avenue Interchange.