Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

1.10.17_CPR-5
January 10, 2017
Four lanes in each direction are now open at the Cottman Avenue Interchange.
12.14.16_BR0-1
December 16, 2016
Workers assemble formwork for support columns for a new ramp from Aramingo Avenue to the Betsy Ross Bridge.
12.14.16_CPR-2
December 16, 2016
Barrels have replaced concrete barriers at the work zone between Cottman Avenue and Bridge Street. Four lanes in each direction are scheduled to be opened between the interchanges this week.
12.14.16_GIR-4
December 16, 2016
Workers install shoring to support the walls of the trench that was excavated for placement of a new sewer main down the middle of Delaware Avenue.
12.14.16_GIR-5
December 16, 2016
Sewer main construction down the middle of Delaware Avenue, one of the utility upgrades that are part of the project to rebuild I-95 at the Girard Avenue Interchange.
12.14.16_GIR-1
December 16, 2016
Continued beam setting for the new northbound viaduct at Girard Avenue
12.14.16_CPR-4
December 16, 2016
A crew finishes median barrier construction at the Cottman Avenue Interchange.
12.14.16_BR0-3
December 16, 2016
Piles are driven in the median area for the foundation of a support pier for a new ramp from Aramingo Avenue to the Betsy Ross Bridge.
12.6.16_BR0-2
December 06, 2016
Late fall sunshine reflects off newly poured concrete on a section of the new on-ramp to I-95 south from Aramingo Avenue.
12.6.16_GIR-4
December 06, 2016
A concrete finisher smooths the edge on a section of recently placed concrete deck on the new northbound viaduct at Girard Avenue.