Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

5.9.17_GIR-2
May 09, 2017
The new northbound off-on ramps at Girard Avenue meet at a new intersection on Richmond Street. The new off-ramp is expected to open later this spring, the new on-ramp this fall.
4.24.17 GIR
April 24, 2017
Workers paint the steel girders on a section of the new I-95 north viaduct at the Girard Avenue Interchange.
4.24.17 BS4
April 24, 2017
Aramingo Avenue traffic at the bridge over Frankford Creek at the Betsy Ross Bridge Interchange
4.24.17 CPR
April 24, 2017
Partially completed but reopened intersection of New State Road and Milnor Street at the Cottman Avenue (Route 73) Interchange.
3.24.17_CPR-2
March 24, 2017
Placing paver blocks to stabilize the embankment at the I-95 Magee Avenue overpass
3.24.17_GIR-2
March 24, 2017
The sub-base is graded for the pavement that will take motorists to the new northbound I-95 on-ramp at the new northbound Girard Avenue Interchange.
3.24.17_BR0-2
March 24, 2017
Continuing construction of the approach from I-95 south to the ramps for Aramingo Avenue and the Betsy Ross Bridge
3.24.17_BR0-1
March 24, 2017
Deck construction for a section of the ramp from I-95 south to Aramingo Avenue
3.24.17_GIR-1
March 24, 2017
A roller is used to compact the sub-base for the pavement that is being built at the new northbound interchange ramps at Girard Avenue.
3.13.17_BR0-1
March 13, 2017
Ironworkers tie re-bars on the deck of the new ramp from Aramingo Avenue to the Betsy Ross Bridge.