Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

7.21.16_BRI-2
July 26, 2016
Concrete paving is in place for a section of the new ramp from Aramingo Avenue to the Betsy Ross Bridge.
7.21.16_BRI-3
July 26, 2016
The new ramp from the Betsy Ross Bridge to Aramingo Avenue awaits deck paving.
7.21.16_CPR-1
July 26, 2016
A section of new northbound pavement at the Cottman Avenue Interchange.
7.21.16_CPR-2
July 26, 2016
Grinding the new northbound concrete pavement at Cottman Avenue for smoothness.
7.21.16_CPR-5
July 26, 2016
The concrete pavement base at the New State Road underpass at the Cottman Aveune Interchange cures.
7.21.16_GIR-1
July 26, 2016
Deck construction on the I-95 north viaduct at Girard Avenue.
7.21.16_GIR-4
July 26, 2016
Beam setting continues to move from north to south for the new I-95 north viaduct at Girard Avenue.
7.6.16_CPR-2
July 08, 2016
A crew sets formwork during installation of curbs and sidewalks under the new I-95 bridge over Unruh Avenue at the Cottman Avenue Interchange.
7.6.16_BR0-11
July 08, 2016
A section of the new concrete deck cures for the new ramp from the Betsy Ross Bridge to Aramingo Avenue.
7.6.16_GIR-3
July 08, 2016
A paving crew places the concrete base for a section of Delaware Avenue at the Girard Avenue Interchange.