Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

8.4.16 BR0-1
August 05, 2016
Workers install fall-protection atop steel beams for the widened section of the ramp from Aramingo Avenue to I-95 south at the Betsy Ross Bridge/Aramingo Avenue Interchange.
8.4.16 GIR-1
August 05, 2016
Access to and from Aramingo Avenue at Delaware Avenue at the Girard Avenue Interchange has been reopened.
8.4.16 BR0-2
August 05, 2016
A temporary causeway into the Frankford Creek will be used to construct a support pier for the new ramp from Aramingo Avenue to I-95 south.
8.4.16 BR0-3
August 05, 2016
Paving the new ramp from the Betsy Ross Bridge to Aramingo Avenue
8.4.16 CPR-1
August 05, 2016
From above, paving at the intersection of Milnor Street and New State Road at the Cottman Avenue Interchange. The triangle in the center will be a raised concrete island.
8.4.16 CPR-4
August 05, 2016
Paving a lane at a time on the widened northbound side of I-95 between Bridge Street and Cottman Avenue.
8.4.16 GIR-3
August 05, 2016
Construction of the new northbound viaduct at Girard Avenue continues to progress south toward Palmer Street.
7.26.16_CPR-6
July 26, 2016
Construction is underway on the new intersection of Milnor Street with New State Road at the Cottman Avenue Interchange.
7.26.16_GIR-3
July 26, 2016
Workers install an expansion dam between sections of the new I-95 north viaduct at the Girard Avenue Interchange.
7.26.16_BRI-1
July 26, 2016
Paving is in place for a temporary ramp that will connect I-95 south with the Betsy Ross Bridge. Traffic will use the temporary ramp while the existing ramp is dismantled and the section of new ramp is built between the main line and the finished new ramp.