Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

9.1.16_GIR-3
August 31, 2016
A longer view of construction at the southern end of the northbound viaduct at the Girard Avenue Interchange shows columns for the new off-ramp as well as piers for the viaduct.
9.1.16_GIR-4
August 31, 2016
Delaware Avenue traffic is diverted around construction of piers for the new northbound off-ramp.
9.1.16_BRi-1
August 31, 2016
New concrete pavement on the new ramp from the Betsy Ross Bridge to Aramingo Avenue: A worker sorts rebar for the ramp's parapets.
9.1.16_BRi-2
August 31, 2016
Workers saw cut the concrete deck for removal as part of the dismantling of the old ramp from I-95 south to the Betsy Ross Bridge.
9.1.16_BRi-3
August 31, 2016
Demolition of the old ramp from I-95 south to the Betsy Ross Bridge: Traffic heading to the bridge is using the new ramp.
9.1.16_BRi-5
August 31, 2016
New deck beams for the new ramp from Aramingo Avenue to I-95 south
9.1.16_CPR-3
August 31, 2016
New northbound paving at the Cottman Avenue Interchange
9.1.16_CPR-4
August 31, 2016
Construction of a new intersection at New State Road and Milnor Street at the Cottman Avenue Interchange.
9.1.16_CPR-1
August 31, 2016
Large sections of new northbound paving are in place between the Cottman Avenue and Bridge Street interchanges.
8.19.16_BR0-5
August 22, 2016
Workers drill grip holes into the parapets on the old I-95 north ramp to the Betsy Ross Bridge. The old ramp is being demolished.