Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

8.8.17_H04-4
August 18, 2017
A crew installs drainage components, the first step in creating a new intersection of Tacony Street and the Adams Avenue Connector.
8.8.17_GIR-1
August 18, 2017
A "T" panel is maneuvered into place as workers build a "T Wall" retaining wall to support the approach to the new northbound off-ramp at the Girard Avenue Interchange.
8.8.17_CPR-4
August 18, 2017
Section of a new storm sewer await installation under Bleigh Avenue at the Cottman Avenue Interchange.
7-19-17_cpr-7
July 21, 2017
A crew finishes a section of sidewalk at the Princeton Avenue extension under I-95.
7-19-17_br0-1
July 21, 2017
Barrels mark the construction zone along Torresdale Avenue near Adams Avenue where PennDOT is installing new water lines as part of the Adams Avenue Connector.
7-19-17_gir-water
July 21, 2017
A water truck sprays the Girard Interchange construction areas to keep the dust down.
6-26-17_gir-1
June 23, 2017
With the old northbound off-ramp removed, excavators are clearing the area to start construction on the southern end of the new northbound viaduct.
6-21-17_gir-2
June 23, 2017
The old retaining wall along I-95 north at Colombia Avenue near the Girard Avenue Interchange is being replaced by the approach to the new northbound off-ramp to Richmond Street.
6-21-17_br0-1
June 23, 2017
Workers position barrier along the new approach to the southbound off-ramp to the Betsy Ross Bridge.
6-12-17_gir-1
June 13, 2017
Demolition of a retaining wall at Columbia Avenue and Richmond Street for construction of the approach to the new northbound off-ramp at Girard Avenue.