Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

10.19.17_CPR-1
October 20, 2017
A crew places sidewalk as part of the reconstruction of Bleigh Avenue at the Cottman Avenue Interchange.
10.19.17_GIR-1
October 20, 2017
The new on-ramp to northbound I-95 from Richmond Street at the Girard Avenue Interchange is now open to traffic.
10.19.17_BR0-1
October 20, 2017
The new intersection of Tacony Street and Adams Avenue, under construction as part of surface street improvements at the Betsy Ross Bridge Interchange.
8.8.17_GIR-5
October 01, 2017
The new on-ramp to I-95 north from Richmond Street at the Girard Avenue Interchange will open later this month as part of a traffic shift onto a section of the new viaduct.
7.19.17_BR0-3
October 01, 2017
The first of two contracts to improve the ramp system at the Betsy Ross Bridge/Aramingo Avenue Interchange will wrap up late this year.
9.18.17_CPR-2
October 01, 2017
A landscaped island separates State Road from New State Road at the Cottman Avenue Interchange.
9.18.17_GIR-1
September 19, 2017
Parapet construction will complete the last section of concrete paving at the approach to the new off-ramp at Girard Avenue.
9.18.17_H04-1
September 19, 2017
With the new water mains installed as part of the Adams Avenue Connector project, a section of Torresdale Avenue in the vicinity of Adams Avenue is being reconstructed.
9.18.17_CPR-3
September 19, 2017
Machinery is in place to complete the switch from the old water main to the new main installed as part of the Cottman Avenue Interchange reconstruction. The apparatus will be removed after the switch, known as a "wet tap".
9.18.17_GIR-2
September 19, 2017
The final section of new concrete pavement at the approach to the new northbound off-ramp at Girard Avenue cures.