• Follow Us on Twitter

Current Progress Photos

Shown below are all the current construction progress photographs of the projects, in reverse chronological order. Enlarged images can be seen by clicking any of these thumbnails.

9.16.19_GIR-3
September 20, 2019
A tarp has been installed to prevent debris from escaping during the demolition of the southbound I-95 viaduct.
9.4.19_GIR-6
September 20, 2019
A crane places deck beams onto the new southbound I-95 viaduct.
9.4.19_AF1-2
September 20, 2019
Removal of SEPTA's existing Route 15 trolley tracks on Richmond Street in Port Richmond.
8.20.19_H04-2
August 26, 2019
A crew finishes installation of the new storm sewer on Torresdale Avenue near the new intersection with the Adams Avenue Connector.
8.20.19_GIR-1
August 26, 2019
Forms are in place as workers prepare to pour the concrete for a pier cap for the new southbound I-95 viaduct at the Girard Avenue Interchange.
8.5.19_GIR-8
August 13, 2019
The new bridge over Aramingo Avenue with a decorative retaining wall.
8.5.19_GIR-2
August 13, 2019
Rebar is in place as crews prepare to pour concrete on the new southbound viaduct.
7.24.19_AFC-2
August 08, 2019
Workers prepare to install new trolley tracks on Richmond Street.
7.24.19_GIR-4
August 08, 2019
Placing a pier cap on one of the dozens of support piers for the new I-95 viaduct.
7.24.19_BS4-2
August 08, 2019
The southbound side of the Aramingo Avenue bridge over the Frankford Creek is finished. Work has briefly shifted to the middle before they proceed to the northbound side.